In March, the construction of the right-turn lane began, which will give great relief to those going from Zsibogó to Szent Anna Street. A few months have passed since March, so we looked at how far the work had progressed at the foot of the Vágóhíd Street overpass.

According to the previous announcement of the local government, the transformation will be completed with government support from almost HUF 100 million, in the hands of Nemzeti Infrastruktúra Fejlesztő Zrt.

Even when we were there, the work was going on a lot. It is a big step forward from the initial stage that it is already clear how the new lane will go. The base of the road is finished, the benches are also mostly in place.

On the section closer to the Wesselényi street intersection, road builders jumped in and out of pits. The machines moved, they dug the ground. Obviously there is still work to be done.

A car crashed into the yard of the building from the Vágóhíd street overpass in Debrecen

We visited the area several times that day. It was not very surprising that the traffic on the Vágóhíd Street overpass did not change compared to the situation in March. In popular periods, traffic jams are constant. The line is often up to Zsibi. It will be a great relief for everyone when the new right turn lane is completed.

The conversion is expected to be completed by August 2021. It is planned that a 147-meter-long foot and bicycle path will be built in parallel.